National Grid update – March 2024
ESO’s East Anglia Networks Study
Thank you for your engagement over the past months on ESO’s East Anglia Network Study.
The ESO has today published their independent study on different network configuration options (both onshore and offshore) in East Anglia region. Please see here for a link.
In total the study considers ten network configuration options in East Anglia and assesses their value against economic, environmental, community and deliverability metrics. Building on engagement with local community groups as part of this study, four of the options were assessed to specifically reflect community preferences.
The study does not make a recommendation but provides additional data on each of these network configurations and their impact on the national electricity network.
The new power flows brought on by the potential change in connection location stemming from the OCSS, has meant that new network configuration options are available for the Transmission Owner to consider should OCSS continue. However, these options assessed within this study come with critical trade-offs to be made.
We thank you for your continued engagement and look forward to receiving any questions you have.
Kind regards,
East Anglia Study Team
C_NG_EA_0032 Poster V2(option1)
The Great Grid Upgrade
National Grid update – June 2023
We are continuing work to support the delivery of new sources of renewable energy to homes and businesses across East Anglia and the UK.
To make it clear that this work is part of The Great Grid Upgrade, we are changing the project name from East Anglia GREEN to ‘Norwich to Tilbury’. All National Grid projects that are part of The Great Grid Upgrade will include specific locations in their names to make it easier for people to understand where we are proposing to build new grid infrastructure.
Norwich to Tilbury is one of a number of projects being developed as part of The Great Grid Upgrade – the largest overhaul of the grid in generations.
Public consultation summer 2023
While we are still at an early stage of developing our proposals, we have made good progress since our consultation last year. We have reviewed all the feedback received and carried out surveys and assessments, alongside holding discussions with various stakeholders. We have made a number of changes and we will soon publish our proposed preferred draft alignment, which will show potential positions for overhead lines and underground cables.
To help reduce uncertainty for local communities, we will hold a second stage of public consultation. This will provide an opportunity for local communities to comment on our proposals in more detail and we will be able to explain how feedback from last year has influenced our work.
Today we are updating our project website with more information about the name change and the progress we have made, as well as producing a short video here. We will shortly be writing to local residents along the route with more information and to invite them to attend one of our public events and webinars to find out more about consultation.
Recently, the Electricity Systems Operator (ESO) announced that it would launch a ‘Study’ to assess objectively the options for Norwich to Tilbury and other proposed network reinforcements across East Anglia. We understand the Study will consider the costs and deliverability of the different options.
I want to reassure you that, in this second stage of consultation, we are not pre-empting the outcome of the ESO Study. This stage of consultation is both necessary and important so that we can continue to hear local views whilst we work to an ambitious programme to deliver this new connection by the end of this decade, in line with the Government’s commitment to connect up to 50 GW of offshore wind by 2030. If the recommendations from the ESO Study should indicate alternative infrastructure options, we will of course review and engage with the impacted communities appropriately.
After this consultation and following the completion of the ESO Study there will be a further stage of consultation next year, where we hope to show finalised proposals informed by both local feedback and the outcomes of the Study.
Following the name change we have also updated our project contact details which you can now use to get in touch with us here:
With best wishes.
Yours sincerely
Donna Burnell
Regional External Affairs Manager
Norwich to Tilbury